Service Directory
New Road Asphalting Request
This service is provided by the Ministry of Works to Individuals, Businesses, Governmental Entities, and NGOs wishing to asphalt new roads.
Required Attachments
- In case of a request from a Governmental Entity, an official letter is to be sent.
Process Time
- 3 to 9 months : in case of availability of sewage service and budget
- two to five years : In case the sanitary service is not available
Service Provider
Ministry of Works
Cooperative Entities
- Electricity and Water Authority
- Urban Planning and Development Authority
- Ministry of Municipalities Affairs and Agriculture
Service Processes
- Applicant: Submit the application along with the required documents and information to the Ministry of Works.
- Ministry of Works: Review the application to ensure that the requested work can be implemented.
- Ministry of Works: Prepare an official response through the same channel through which the application was submitted.
- Ministry of Works: In case of approval, the request work would be implemented.
- Applicant: Submit the application along with the required documents and information to the Ministry of Works.
- Ministry of Works: Review the application to ensure that the requested work can be implemented.
- Ministry of Works: Prepare an official response through the same channel through which the application was submitted.
- Ministry of Works: In case of approval, the request work would be implemented.