Request for additional electric power load (High Voltage)
Service to request additional electric power loads
Required Attachments
- Electricity supply request form
- Power conditions requirement for building permits
- Building permit from the municipality
- Copy of the title deed
- Copy of the aerial map
- Copy of the survey certificate
- Copy of the address card
- Details of the required electrical loads
- Confirmation form for the electricity supply’s power load from the main developer for private projects
Legal Regulations
- Resolution No. 13 of 2006 related to the regulations of charges for the delivery of electricity and water services.
- Decree No. 2 of 2010 on the electrical wiring system
Fees
- Depends on the project : -
Process Time
- 71 Working Days
Service Provider
Electricity and Water Authority